New York / New Jersey
New York has the first statewide pause in force, and New Jersey has new cost-allocation law and dozens of local moratoria (counts vary by tracker). This is a latency and enterprise market, not a place for gigawatt campuses.
CBRE H1 2026: NY Tri-State 190.0 MW inventory [Cushman & Wakefield, 2026 Global Data Center Market Comparison (Americas rankings) (2026-05); CBRE press release: demand continues to outpace supply (H1 2026 market table) (2026-08)]
Power and the queue
- FERC accepted PJM's Large Load definition and registry (ER26-3515), effective Oct 12, 2026. This covers the New Jersey utilities. [FERC order ER26-3515 on PJM Large Load definition and registry (2026-10-09)]
- NJ Data Center Fair Share Act (P.L. 2026, c.32, effective Jul 7, 2026): utilities must file large-load tariffs for 100 MW+ data centers. BPU RFI comments are due Nov 13, 2026. [New Jersey P.L. 2026, c.32 (A796) Data Center Fair Share Act (2026-07-07); NJ BPU: Data Center Fair Share Act request for information notice (2026-10)]
Notable projects owners where public
- Anthropic/Fluidstack custom data center in New York (part of the $50B plan). The exact site is not confirmed by Anthropic.uncertain [Anthropic: invests $50 billion in American AI infrastructure (Fluidstack, Texas and New Yo (2025-11)]
Regulatory posture incentives, moratoria, zoning, water, large-load rules
- NY Executive Order 62 (Jul 14, 2026): a one-year pause on state permits for new data centers of 50 MW or more while agencies build a framework. The Legislature separately passed a 20 MW moratorium bill. The Anthropic S-1 names New York's pause as a risk. [NCSL: New York hits pause on data centers. Will other states follow? (2026-07-15); NCSL: Which States Are Banning Data Centers? (updated Sep 15, 2026) (2026-09-15); Anthropic, PBC Form S-1/A (Amendment No. 1), filed with the SEC Nov 2, 2026 (2026-11-02)]
- NJ bills: A5482 (6-month moratorium) was introduced. Prevailing wage now applies to some DC construction (S4928). A water/energy usage reporting bill passed both chambers. [NCSL: Which States Are Banning Data Centers? (updated Sep 15, 2026) (2026-09-15); Moratorium Nation dataset (M. Bommarito, CC BY 4.0), current through Sep 23, 2026 (2026-09-23)]
- Gov. Hochul was re-elected Nov 3, so the EO framework is likely to continue. [DCD: Anti-data center candidates claim victory across the US in 2026 midterm elections (2026-11-04)]
Pending legislation and actions 14 items
| Date | Jurisdiction | Item | Status | Impact | Source |
|---|---|---|---|---|---|
| 2026-06-04 | New York state | AB 10141 / SB 9144 (and AB 11560 / SB 10642)uncertain Legislative one-year moratorium on data centers over 20 MW, plus a DEC statewide environmental impact report. Passed the Legislature on Jun 4, 2026. NCSL and an ND legislative memo cite different bill numbers. | passed legislature | high | [NCSL: Which States Are Banning Data Centers? (updated Sep 15, 2026) (2026-09-15)] |
| 2026-06-30 | New Jersey state | S3379 / A4096 / A4696 (2026-2027) Requires semi-annual data center water and energy usage reports to BPU for three years, with performance metrics for data centers receiving state incentives. | passed legislature | medium | [NJ Legislature bill history API - S3379 (2026-2027)] |
| 2026-06-01 | New York state | S6394A / A9086A (2025-2026) New York State Sustainable Data Centers Act. Requires data center disclosure reporting, public engagement, energy and water reporting, renewable-energy requirements, and surcharge or discount mechanisms tied to affordability and grid impacts. | pending | low | [NY Senate Bill S6394 (2025-2026)] |
| 2026-06-01 | New York state | S8540 / A9039A (2025-2026) "Accountability of Costs for Data Centers Act" or "AC/DC Act." Creates separate utility classification and tariff treatment for large energy-use facilities so data centers bear proportional or directly assigned service costs. | pending | low | [NY Senate Bill S8540 (2025-2026)] |
| 2026-03-23 | New Jersey state | SR18 (2026-2027) Urges PJM-region states and the District of Columbia to adopt policies requiring data centers to obtain electricity from new zero- or low-emission sources. | pending | low | [NJ Legislature bill history API - SR18 (2026-2027)] |
| 2026-03-16 | New Jersey state | A3966 (2026-2027) Directs DEP to study short- and long-term effects of large-scale data center water use. | pending | low | [NJ Legislature bill history API - A3966 (2026-2027)] |
| 2026-03-16 | New Jersey state | A4710 (2026-2027) "Clean Energy AI Incentivization Act"; directs BPU to create standards and incentives for AI data centers that bring self-sufficient clean energy. | pending | low | [NJ Legislature bill history API - A4710 (2026-2027)] |
| 2026-03-16 | New Jersey state | S680 / A1170 (2026-2027) Requires BPU approval of energy usage plans for proposed AI data centers and cryptocurrency mining facilities; requires electricity from new clean energy sources after a PJM-region trigger is met. | pending | low | [NJ Legislature bill history API - S680 (2026-2027)] |
| 2026-02-19 | New Jersey state | S3611 (2026-2027) Amends the MLUL to require planning boards to submit certain data center applications to the State Planning Commission and BPU; requires State Planning Commission approval; excludes data centers from economic development subsidies. | pending | low | [NJ Legislature bill history API - S3611 (2026-2027)] |
| 2026-01-30 | New York state | S8546 / A10049 (2025-2026) Establishes a grid modernization surcharge for covered data centers and high-intensity data centers, with revenues directed to grid reliability, capacity expansion, and clean-energy integration. | pending | low | [NY Senate Bill S8546 (2025-2026)] |
| 2026-01-07 | New York state | S8037 (2025-2026) Establishes dedicated utility treatment for data centers, including rate classification, targeted congestion management, and off-grid connection provisions. | pending | low | [NY Senate Bill S8037 (2025-2026)] |
| 2026-01-07 | New York state | S8518 / A9138 (2025-2026) Imposes an excise tax on electricity used in proof-of-work digital asset mining, with exemptions for lower-consumption and off-grid renewable operations. | pending | low | [NY Senate Bill S8518 (2025-2026)] |
| 2026-01-07 | New York state | S8536 / A9064 (2025-2026) Bars electric and gas corporations from passing costs or increasing charges due to data center or semiconductor facility buildout except to ratepayers involved with those facilities. | pending | low | [NY Senate Bill S8536 (2025-2026)] |
| 2026-01-07 | New York state | S8645 / A9136 (2025-2026) S8645 addresses carbon reduction planning and data center/BESS siting. A9136 requires new data centers to assess and incorporate thermal energy networks for waste-heat reuse. | pending | low | [NY Senate Bill S8645 (2025-2026)] |
In force / enacted 9 items
| Date | Jurisdiction | Item | Status | Impact | Source |
|---|---|---|---|---|---|
| 2026-10-09 | PJM (13 states + DC) utility | FERC order ER26-3515: PJM Large Load definition and registry FERC accepted the definition and registry, effective Oct 12, 2026, and rejected the rest of the filing. The registry is not a public per-request queue. | enacted | high | [FERC order ER26-3515 on PJM Large Load definition and registry (2026-10-09)] |
| 2026-08-25 | Town of Orangetown town | Town of Orangetown Local Law No. 5 of 2026, adding Article XX to Chapter 43 (Zoning) Adopted Duration: 180 days, renewable once for an additional 180 days by Town Board resolution | in force | high | [Local Law 5-2026 Temporary Town-Wide Moratorium (Adopted 8-25-2026)] |
| 2026-07-20 | Sayreville town | Ordinance 15-26 (Borough of Sayreville), a temporary prohibition on data center development in every zone, including the Hercules Redevelopment Area, for 18 months, introduced 2026-06-15 and adopted o Duration: 18 months from adoption; the ordinance also requires publication and mayoral approval, and the copy reviewed does not show the mayoral approval date | in force | high | [Borough of Sayreville] |
| 2026-07-14 | New York state | Executive Order No. 62 (2026) A one-year pause on state permits for new data centers with peak demand of 50 MW or more, while agencies develop a long-term framework. It is the first statewide pause in force, and Anthropic's S-1 names it as a risk. | in force | high | [NCSL: New York hits pause on data centers. Will other states follow? (2026-07-15)] |
| 2026-07-07 | New Jersey state | Data Center Fair Share Act, P.L. 2026 c.32 (A796/S731) Utilities must file large-load tariffs for data centers of 100 MW or more within 180 days after BPU standards. BPU RFI comments are due Nov 13, 2026. | enacted | high | [New Jersey P.L. 2026, c.32 (A796) Data Center Fair Share Act (2026-07-07)] |
| 2026-06-10 | Asbury Park city | Resolution 2026-264, a council resolution (not a zoning ordinance)uncertain Duration: Pause on local data center applications/site plans until the city completes its zoning code rewrite | in force | high | [https://www.wbjb.org/local-news/2026-06-19/asbury-park-calls-for-moratorium-on-ai-data-cen] |
| 2022-11-22 | New York state | S6486D / A7389C (2021-2022, enacted) Enacted a two-year moratorium on DEC permits for certain fossil-fueled proof-of-work cryptocurrency mining operations and required a generic environmental impact statement. | enacted | high | [NY Assembly Bill A07389 action history (nyassembly.gov)] |
| 2026-01-20 | New Jersey state | S4928 (2024-2025) Applies prevailing wage requirements to certain data center construction activity. | enacted | medium | [NJ Legislature historical bill history API - S4928 (2024-2025)] |
| 2025-07-08 | New Jersey state | A5466 (2024-2025) Requires BPU study and report on data center electricity cost impacts. | enacted | medium | [NJ Legislature historical bill history API - A5466 (2024-2025)] |
Pricing & supply snapshot directional
MW Desk estimate / directional range, Q4 2026
Asking-rate bands below are MW Desk directional estimates in USD per kW-month. They are rounded ranges, not quoted rates, and they go stale quickly.
- Retail colo (roughly 0–250 kW): $155–455/kW-mo
- Wholesale (roughly 250 kW–4 MW): $130–290/kW-mo
- Large / hyperscale blocks (roughly 4 MW+): $135–245/kW-mo
- Vacancy band: around 5–8% (moderately available)
- Commissioned inventory (directional): ~420–530 MW
- Available power (directional): ~10–45 MW
- Under construction: ~40–110 MW
- Planned pipeline: ~165–235 MW
- Absorption: light positive absorption
- Power / timing: Mix of tight wholesale and some retail availability; large contiguous blocks still require lead time.
Blends New York City-area and Northern New Jersey bands.
Indicative only. Ranges are rounded and adjusted directional estimates, not quoted asking rates or a survey. Confirm with brokers and operators before acting. Source data ages quickly.