INDEPENDENT DATA CENTER INTELLIGENCERESEARCH SNAPSHOT · NOV 05, 2026 · PST
Markets / Houston
C&W 2026 Americas · Tertiary #3 · updated 2026-11-05

Houston

A big eligible queue, but it is frozen like the rest of ERCOT. Gulf Coast gas supply is an advantage once the audit clears.

mixedGrid: CenterPoint Houston Electric (ERCOT)

[Cushman & Wakefield, 2026 Global Data Center Market Comparison (Americas rankings) (2026-05)]

Power and the queue

Notable projects owners where public

No verified public item yet. This is a gap we are working on.

Regulatory posture incentives, moratoria, zoning, water, large-load rules

Pending legislation and actions 1 items

DateJurisdictionItemStatusImpactSource
2026-11-04Texas
state
Governor-elect pledge: statutory moratoriumuncertain
Gina Hinojosa (elected Nov 3) campaigned on an immediate moratorium lasting until the Legislature passes protections. BMI says the pause could plausibly extend into late 2027.
proposedhigh[DCD: Anti-data center candidates claim victory across the US in 2026 midterm elections (2026-11-04)]

In force / enacted 3 items

DateJurisdictionItemStatusImpactSource
2026-09-21Texas
state
Governor directive: TCEQ to halt data center permits
TCEQ is to issue no permits for infrastructure directly supporting data centers until ERCOT's audit is complete. TCEQ reported compliance on Oct 19, and a watchdog says some permits still advanced.
in forcehigh[Office of the Texas Governor: Governor Abbott directs TCEQ to halt data center permits (2026-09-21)]
2026-08-03Texas
state
Governor directive: comprehensive data center audit (ERCOT Batch Zero)
PUCT/ERCOT must verify and audit data centers in the interconnection queue. ERCOT is not approving energization of new data center and crypto loads of 75 MW or more until the audit is complete. Verification and community-impact reports are due Dec 10, 2026.
in forcehigh[Office of the Texas Governor: Governor Abbott directs comprehensive data center audit (2026-08-03)]
2025-06-20Texas
state
SB 6 (89R, 2025)
Requires PUCT/ERCOT large-load planning and interconnection standards; applies to large loads at a default 75 MW single-site threshold; addresses interconnection studies, cost allocation, co-location, and emergency curtailment
enactedhigh[SB 6 (89R, 2025) primary source (2025-06-20)]

Open the full TX tracker →

Pricing & supply snapshot directional

MW Desk estimate / directional range, Q4 2026

Asking-rate bands below are MW Desk directional estimates in USD per kW-month. They are rounded ranges, not quoted rates, and they go stale quickly.

  • Retail colo (roughly 0–250 kW): $120–350/kW-mo
  • Wholesale (roughly 250 kW–4 MW): $110–195/kW-mo
  • Large / hyperscale blocks (roughly 4 MW+): $95–210/kW-mo
  • Vacancy band: around 5–8% (moderately available)
  • Commissioned inventory (directional): ~245–355 MW
  • Available power (directional): ~0–35 MW
  • Under construction: ~20–130 MW
  • Planned pipeline: ~0.4–0.9 GW
  • Absorption: solid positive absorption
  • Power / timing: Mix of tight wholesale and some retail availability; large contiguous blocks still require lead time.

Indicative only. Ranges are rounded and adjusted directional estimates, not quoted asking rates or a survey. Confirm with brokers and operators before acting. Source data ages quickly.

TJ field notes

Coming soon: TJ's on-the-ground notes on this market. Expect what the queue really looks like, which sites can actually get power, and what the brokers aren't saying.

Slot reserved for TJ's detailed market report.