Atlanta + Georgia secondary
The construction lead is real, but the political floor just moved. A governor-elect promising a statewide pause, plus 50+ local moratoria in force across Georgia, put projects starting in 2028 and later at risk. Projects already under construction with Georgia Power contracts are the safe tier.
CBRE H1 2026: #1 in North America for capacity under construction (2,882 MW) [Cushman & Wakefield, 2026 Global Data Center Market Comparison (Americas rankings) (2026-05); CBRE, North America Data Center Trends H1 2026 (2026-08)]
Power and the queue
- CBRE H1 2026: 1,803.2 MW inventory and 2,882 MW under construction, up 52.3% YoY. Atlanta passed Northern Virginia in construction for the first time. [CBRE, North America Data Center Trends H1 2026 (2026-08); CBRE press release: demand continues to outpace supply (H1 2026 market table) (2026-08)]
- Georgia PSC certified about 9.985 GW of new generation, around 80% of it expected to serve data centers, with Georgia Power backstopping costs through 2031. [Georgia PSC: Data Center Fact Sheet (Sep 2026) (2026-09)]
Notable projects owners where public
- Microsoft Fairwater Atlanta AI datacenter, operating since Oct 2025 and linked with Fairwater Wisconsin. [Microsoft: From Wisconsin to Atlanta, Microsoft connects datacenters to build its first AI (2025-11)]
- Project Sail, Coweta County: about 900 MW (Prologis/Atlas), approved Apr 2026, per an aggregator.uncertain [Apollo Technical: Data Centers in Georgia, 2026 map and project tracker (aggregator) (2026-11-05)]
- Stargate 'Project Camellia' (Georgia): an approved 3.2 GW power contract running 2028 to 2032, still at the contracted stage.uncertain [Stargate.how: October status check, where every Stargate site stands (2026-10-18)]
Regulatory posture incentives, moratoria, zoning, water, large-load rules
- DeKalb County: the moratorium on new or expanded data center applications was extended Jul 7, 2026 to Mar 30, 2027, and is under lawsuit. [DeKalb County BOC item 2026-1109 (moratorium extended to Mar 30, 2027) (2026-07-07); Programs.com: Data Center Moratoriums by State tracker (2026) (2026-11-05)]
- City of Atlanta (Sep 3, 2024): data centers are barred in the Beltline Overlay and within 2,640 ft of high-capacity transit stations. [Atlanta City Council: data center ordinances (Beltline overlay, transit areas) (2024-09-03)]
- Governor-elect Keisha Lance Bottoms (elected Nov 3) pledged a temporary statewide pause. State moratorium bills HB 1012 and HB 1059 died in 2026. [DCD: Anti-data center candidates claim victory across the US in 2026 midterm elections (2026-11-04); NCSL: Which States Are Banning Data Centers? (updated Sep 15, 2026) (2026-09-15); Programs.com: Data Center Moratoriums by State tracker (2026) (2026-11-05)]
- The sales-tax exemption survived a 2026 repeal push (SB 410). Certificates expire Dec 31, 2031. [LoadAtlas: Data center tax incentives by state, and what changed in 2026 (2026-10-21)]
Pending legislation and actions 1 items
| Date | Jurisdiction | Item | Status | Impact | Source |
|---|---|---|---|---|---|
| 2026-11-04 | Georgia state | Governor-elect pledge: temporary statewide pauseuncertain Keisha Lance Bottoms (elected Nov 3) called for a statewide pause to assess impacts on bills, communities and the environment. | proposed | high | [DCD: Anti-data center candidates claim victory across the US in 2026 midterm elections (2026-11-04)] |
In force / enacted 22 items
| Date | Jurisdiction | Item | Status | Impact | Source |
|---|---|---|---|---|---|
| 2026-09-01 | Georgia PSC / Georgia Power utility | Certification of about 10 GW of new generationuncertain About 9.985 GW certified, roughly 80% expected for data centers, with Georgia Power backstopping costs through 2031. | enacted | high | [Georgia PSC: Data Center Fact Sheet (Sep 2026) (2026-09)] |
| 2026-08-31 | Forest Park city | Forest Park City Council 90-day data center moratorium (instrument number not published)uncertain Council adopted a 90-day moratorium at a special called meeting. Duration: 90 days (to about 2026-11-29) | in force | high | [News-Daily (Clayton County) (2026-08-31)] |
| 2026-08-13 | Ball Ground city | Ball Ground City Council moratorium on data center applications (instrument and term not published in accessible sources) City Council adopted a moratorium on data center applications. Duration: 180 days (effective 2026-08-14 through 2027-02-09), per Cherokee Tribune reporting; not independently verified against the moratorium's own text, which was not located separately from the | in force | high | [City of Ball Ground, Georgia (2026-08-13)] |
| 2026-07-28 | Paulding County county | Paulding County Board of Commissioners resolution suspending new data center applications, zoning requests, and civil plan reviews Commissioners unanimously approved a moratorium in effect until January 1, 2027, suspending new data center applications, zoning requests, and civil plan reviews Duration: Until January 1, 2027 | in force | high | [Paulding County hits pause on new data centers (2026-08-03)] |
| 2026-07-22 | Cherokee County county | Cherokee County Board of Commissioners resolution instituting a 30-day moratorium on data center applications (July 2026), extended by a Board resolution adopted 2026-08-18 enacting a 180-day moratori Board unanimously adopted a 30-day moratorium in July 2026 and on 2026-08-18 unanimously extended it by 180 days while staff research and draft data center standards. Duration: Initial 30 days (adopted 2026-07-21/22); extended by 180 days on 2026-08-18, for a | in force | high | [North Georgia Community Action Network (2026-08)] |
| 2026-07-21 | Chamblee city | Chamblee City Council temporary moratorium suspending acceptance of applications relating to new data centers (sponsored by At-Large Councilmember Jimmy Furst) Council adopted a 180-day moratorium on data center applications to review its code. Duration: 180 days, through 2027-01-16 | in force | high | [Decaturish (2026-07-21)] |
| 2026-07-07 | DeKalb County county | Moratorium on new or expanded data center applications (extended) Extended Jul 7, 2026 to Mar 30, 2027 and under lawsuit. | in force | high | [DeKalb County BOC item 2026-1109 (moratorium extended to Mar 30, 2027) (2026-07-07)] |
| 2026-07 | Marietta city | Marietta City Council resolution/ordinance adopting a 6-month moratorium on new data centersuncertain City council unanimously voted to pass a six-month moratorium on new data centers through December 31, 2026 Duration: 6 months, through December 31, 2026 Current end: 2026-12-31. | in force | high | [Marietta City Council approves data center off Delk Road (2026-08-12)] |
| 2026-06-16 | Coweta County county | (second instrument, June 2026) Coweta County Board of Commissioners resolution imposing a 180-day moratorium on acceptance of permits, land use amendments, rezoning/conditional use and variance applic Commissioners unanimously adopted a 180-day moratorium to review the county's data center ordinance. Duration: 180 days (to about 2026-12-13) | in force | high | [Times-Herald (Newnan) (2026-06-16)] |
| 2026-06-15 | Milton (Fulton County) city | City Council resolution enacting a 30-day pause on data center applications and permits, subsequently extended City Council unanimously enacted a 30-day moratorium June 15, bridged it with a short extension July 6, and extended it for up to 180 days on July 20 Duration: Initial 30-day moratorium enacted 2026-06-15; bridged by a short housekeeping extension on 2026-07-0 | in force | high | [Milton extends data center freeze for 180 more days (2026-07-20)] |
| 2026-03-23 | Cedartown city | Cedartown City Commission Resolution 4, 2026, adopted March 23, 2026 (unanimous).uncertain Study moratorium; outcome pending as of sources reviewed Duration: Six months per the city manager's public statement ahead of the vote. | in force | high | [Special Call Meeting Minutes, March 23, 2026 (2026-03-23)] |
| 2026-03-03 | Carroll County county | Carroll County Board of Commissioners resolution adopted March 3, 2026, applicable only to unincorporated Carroll County; extension resolution adopted June 3, 2026. Third 100-day moratorium adopted 2026-08-04; permanent ordinance for data centers, solar and battery storage still in draft. Duration: 100 days from March 3, 2026 (or until zoning revisions adopted); extended 100 days on June 3, 2026; a third 100-day moratoriu | in force | high | [Carroll County Board of Commissioners Resolution, March 3, 2026 (2026-03-03)] |
| 2026-02-26 | Hall County county | Hall County Board of Commissioners moratorium on detention centers, high-density developments, and data centers, voted 2026-02-26 (per WSB-TV reporting and GPB Georgia Today 2026-02-27); resolution nuuncertain Moratorium extended 2026-08-27 to 2027-02-23; data center ordinance adopted within the UDC update on 2026-09-10 while the moratorium stays in place. Duration: 180 days from 2026-02-26; extended another 180 days by 5-0 vote on 2026-08-27, running until 2027-02- | in force | high | [Hall County extends moratorium on data centers, detention centers (2026-08-27)] |
| 2026-02-24 | Cobb County county | Board of Commissioners moratorium resolution adopted unanimously 2026-02-24; extended by resolution adopted 2026-08-11 (BOC Regular Meeting agenda item 27, 'To adopt a resolution extending a temporary Moratorium extended 2026-08-11 through 2027-02-24; zoning code amendments for data centers being drafted. Duration: Initial 180 days from 2026-02-24; extended another six months by resolution adopted 2026-08-11, expiring 2027-02-24. Current end: 2027-02-24. | in force | high | [Cobb County BOC (2026-08-11)] |
| 2026-02-24 | Meriwether County county | Meriwether County Board of Commissioners moratorium on data center applications in unincorporated areas, extended by action of 2026-07-28 (instrument numbers not published) Commission adopted a moratorium on new data center applications and extended it to 2026-11-21 pending an ordinance. Duration: Original term to 2026-08-23; extended 90 days on 2026-07-28 through 2026-11-21 Current end: 2026-11-21. | in force | high | [Commission extends temporary moratorium on data centers 90 days while drafting ordinance] |
| 2026-02-17 | Newton County county | Resolution R-040726b County study and ordinance drafting Duration: Initial emergency moratorium to 2026-03-18; revised to 2026-04-08; extended to 2026-10-07 Current end: 2026-10-07. | in force | high | [Newton County BOC (2026-04-07)] |
| 2026-02 | Hogansville city | City Council moratorium on data center applications, extended by council votes 2026-05-04, 2026-07-20 and 2026-08-17 (5-0)uncertain Council repeatedly extended its data center application moratorium while revising the UDO; denied the draft ordinance 2026-08-17. Duration: Series of short extensions: 90 days (May 4), 30 days from Aug 2 (July 20), to the Sept 8, 2026 council meeting (Aug 17) | in force | high | [Public Hearing & Regular Meeting Agenda, September 8, 2026 (2026-09-08)] |
| 2026-01-13 | Rockdale County county | Rockdale County Resolution No. 2026-01 (moratorium on data centers and battery energy storage systems), extended 2026-05-12 and amended by Resolution No. R-2026-24 (adopted 2026-08-25), which exempts County extended its data center moratorium through 2026-09-08 and held a public town hall the same evening Duration: Resolution 2026-01 (2026-01-13); extended 2026-05-12 through 2026-09-08; amended by R-2026-24 (2026-08-25) to run through 2026-10-01, the inten | in force | high | [Rockdale County BOC (2026-08-25)] |
| 2026-01 | East Point (Fulton County) city | City Council voice-vote extension of an existing data center moratoriumuncertain City Council extended its existing data center moratorium for three months and directed staff to report back during that period; council considered six months but the city attorney recommended no more than three additional months Duration: Extended three month | in force | high | [Jan 05, 2026 City Council - East Point, GA (2026-01-05)] |
| 2025-09-16 | Lamar County county | Lamar County Resolution 2025-18, 'Moratorium on Commercial and Manufacturing Development,' adopted September 16, 2025; extended as to data centers by Resolution 26-03, adopted on or about March 17, 20 Code modernization including data-center treatment Duration: 180 days (Resolution 2025-18), with an internal staff goal of completing the underlying code rewrite within 90 days; subsequently extended as to data centers specifically by Resolution 26-03 (on or a | in force | high | [Regular Business Meeting Summary, March 17, 2026 (2026-03-17)] |
| 2025-09-03 | Clayton County county | Resolution 2025-193 (per Clayton County news release referenced in GPB 2025-10-22 reporting) [VERIFY: county news release URL https://www.claytoncountyga.gov/news/clayton-county-board-of-commissionersuncertain Study period; permanent post-expiration framework not confirmed Duration: 120 days, through 2025-12-31; extended a total of three times since September 2025 per county documents cited by WABE (July 24, 2026); still in effect as of that date. Exact current end | in force | high | [South 75/85 News (2026-08)] |
| 2024-09-03 | Atlanta city | Data centers barred in Beltline Overlay and near transit Bars data centers in the Beltline Overlay and within 2,640 ft of high-capacity transit stations. | in force | medium | [Atlanta City Council: data center ordinances (Beltline overlay, transit areas) (2024-09-03)] |
Pricing & supply snapshot directional
MW Desk estimate / directional range, Q4 2026
Asking-rate bands below are MW Desk directional estimates in USD per kW-month. They are rounded ranges, not quoted rates, and they go stale quickly.
- Retail colo (roughly 0–250 kW): $145–360/kW-mo
- Wholesale (roughly 250 kW–4 MW): $95–230/kW-mo
- Large / hyperscale blocks (roughly 4 MW+): $100–205/kW-mo
- Vacancy band: around 1–2% (very tight)
- Commissioned inventory (directional): ~2.3–2.8 GW
- Available power (directional): ~5–50 MW
- Under construction: ~65–135 MW
- Planned pipeline: ~2.9–3.6 GW
- Absorption: strong positive absorption
- Power / timing: Immediate powered shell is scarce; expect multi-year waits for net-new large-load service in constrained pockets.
Indicative only. Ranges are rounded and adjusted directional estimates, not quoted asking rates or a survey. Confirm with brokers and operators before acting. Source data ages quickly.