INDEPENDENT DATA CENTER INTELLIGENCERESEARCH SNAPSHOT · NOV 05, 2026 · PST

RESEARCH PREVIEW / NOVEMBER 5, 2026

The delivery constraint.

Power, credit and permission are distinct workstreams. A research note ahead of the planned November 9 first Monday brief—not a sent or finalized issue.

An announcement creates a pipeline. A contract creates an obligation. Neither proves that the megawatts are energized.

The power plant becomes part of the plan.

Google’s Wyoming announcement describes a contracted 702 MW fuel-cell development with carbon capture. The release does not disclose the campus IT load. Generation MW should not be relabeled as server capacity.

Google, November 5 — primary announcement ↗

Existing infrastructure is a head start, not a finish line.

Drax and its partners target an initial phase of up to 100 MW from Q1 2028. The release explicitly keeps planning, regulatory and network approvals, and a suitable tenant as conditions. Its estate-level grid-access figure is a different measure.

Drax, November 3 — project phases and conditions ↗

Finance the right risk.

Crusoe’s equipment facility and EdgeCore’s asset-backed financing show different capital structures: power equipment versus stabilized, leased capacity. Compare what backs the funding, not just how large the headline is.

Crusoe, October 22 ↗ · EdgeCore, October 28 ↗

A faster connection can come with conditions.

CAISO’s board-approved proposal describes flexible interim load interconnection while associated network upgrades are completed. It goes to FERC for review; it is not a promise of unconditional firm service at every site.

California ISO, October 28 ↗

Market pulse: keep the bases separate.

Selected source figures, November 2026. Not additive or a market-capacity total.
Market / sourceWhat is actually statedWhat it does not establish
Wyoming / Google, Nov 5 ↗Contracted 702 MW fuel-cell development with CCS.A disclosed campus IT-load figure or completed plant.
Alliant / DCD, Nov 2 ↗Reported 3.4 GW of contracted data center demand; further contracts expected.That all contracted load is already energized or available to a new buyer.
North Yorkshire / Drax, Nov 3 ↗Initial phase targets up to 100 MW from Q1 2028.Final planning/network approval, a secured tenant or completed operation.
California / CAISO, Oct 28 ↗Board-approved flexible interim interconnection proposal, headed to FERC.Unconditional firm service, blanket approval or a market wait-time guarantee.
Silicon Valley / EdgeCore, Oct 28 ↗Asset-backed financing supported by a stabilized 36 MW IT-capacity building.That the financed capacity is available inventory on this website.

What we are not scoring yet.

Day2GW is our planned time-to-power framework. We are withholding a number until comparable, sourced commitment and energization dates support one. That is a deliberate data-quality decision, not missing zero capacity.

Read the proposed methodology → · Explore the full monthly archive →

Desk analysis, not investment, legal or engineering advice. Source claims and delivery plans can change. Corrections: [email protected].